Milan Multi-Site Campus Data Centre Project
Multi-Site. Full Design to RIBA 4. One Integrated Programme. That’s the Black & White Way.
- Sector
- Multi-Campus Data Centre
Black & White Engineering served as Lead Designer for a multi-site engagement spanning Milan and surrounding municipalities, delivering complete design and permitting services through RIBA Stage 4. The programme required a consistent design framework across multiple locations while accommodating the specific requirements of each site.
The Brief
The appointment covered campus masterplanning through to full RIBA Stage 4 design and permitting across multiple sites. With eight data halls per site and a block redundant electrical topology, the design needed to deliver both technical rigour and flexibility across a geographically dispersed programme.
Our Approach
Campus Masterplanning
Black & White led the masterplanning process across the full campus, establishing a coordinated framework that could be applied consistently across sites while accommodating local planning and permitting requirements at each location.
Standardised Technical Design
A standardised electrical and mechanical design approach was applied across all sites enabling design efficiency and consistency without rigidity.
Permitting Across Multiple Jurisdictions
Permitting services were managed in-house across Milan and surrounding municipalities, navigating local authority requirements at each site as part of the integrated design programme.
The Result
• Over 45MW IT capacity across multiple sites, delivered through a single integrated programme
• Campus masterplan completed, providing a coordinated framework across all locations
• Full RIBA Stage 4 design completed across all sites
• Permitting managed across Milan and surrounding municipalities
• Design features include LV generators, electrical power pods and air-cooled chillers with 6+1 block redundant topology